Posted by in News.


Week beginning 4th February

  • Night work will continue on Monday 4th February — 8pm–6am Monday to Thursday only — No night work Friday 8th February. Work will be on main road from Summerfield to SuperValu.
  • Road resurfacing will be done on Tuesday 12th February 9.30pm to 3.30pm. Stop/Go system will be in operation.
  • Montiagh Road is closed from Monday 4th February for approximately 3 weeks. The road will be closed Monday–Friday day and night and will open Friday evening to Monday mornings for the duration of the works. Road signs are in place on main road to alert drivers to road closure.

There is a possibility that road works may have to revert to day work week beginning 11th February due to extent of services under the road around T junction. It is hoped that this will be avoided but is a possibility.